CFE Fibra E plans to raise $2.473 billion for 60 transmission projects
CFE Fibra E plans to raise $2.473 billion for 60 transmission projects through 2030. Review the annual schedule, the $867 million offering and what it opens up for afores.
CFE Fibra E, the infrastructure trust of the Comisión Federal de Electricidad that trades on the Mexican Stock Exchange, plans to raise $2.473 billion to fund 60 electricity transmission projects under the 2026-2030 Expansion Plan, according to El CEO. The figure was presented by Cajeme Villarreal, chief executive of CFE Capital, the financial arm that manages the vehicle, at the Power Summit organized by Citi.
The instrument already has a track record. In September 2025, the Fibra placed its first bond for $725 million at 15 years, with 240 international investors, according to the same report. On November 10, 2026, CFE Capital began meetings with investors for a follow-on public offering of approximately 451 million trust certificates, with a base amount of $580 million expandable to $867 million, Infobae reported based on EFE. The International Finance Corporation is evaluating an acquisition of up to $80 million, with no confirmed commitment. The vehicle allows afores and institutional investors to participate in transmission revenue, a segment whose operation remains in the hands of the CFE.
The contribution schedule is staggered: $553 million in 2026, $1.135 billion in 2027, $417 million in 2028, $185 million in 2029 and $183 million in 2030, adding up to the $2.473 billion. The full transmission program is around $8 billion, and Forbes México reported on October 1, 2026 that 50 of more than 154 projects are already underway, with an estimated investment of $6.9 billion by 2030. Villarreal said the segment generates revenue of nearly $5 billion a year, resources that allow part to be allocated to capex. Almost half of the plan's investments are financed off the CFE's balance sheet.
For an operator, the data leaves three fronts: a route to regulated cash flow exposure for afores and funds, a construction schedule that opens competitive processes for suppliers and builders, and a test of execution on the annual placements. The next verifiable milestone is the closing of the follow-on offering and its final amount.